Nutone Plant Building 7 Interior Demolition

Cincinnati, OH

Scope of Work:

Selective Demolition, Interior Demolition

Project Detail:

Interior gut out and selective demolition of Building No. 7 at the former Nutone Manufacturing Plant for MedPace’s Corporate Headquarters. This project encompassed the complete removal of  the top (steel) floor and roof of an existing warehouse.  The entire structural floor slab was planed between 1/ 4” and 1/8” in preparation for a new topping slab.  The remainder of the building was deconstructed back to the structural columns and slabs.  The building structure will eventually be converted to a combination parking garage and new office building.