Philip Morris Stemmery Plant Demolition
Location: Louisville, KY
Scope of Work:
Asbestos Abatement, Selective Demolition, Structural Demolition, Excavation, Landscaping
Project Detail:
Structural demolition of the former Stemmery Plant Building. O’Rourke saved the center portion of the building that was connected to other warehouses for future restoration via selective demolition methods. Work was performed around an active electric substation and communication hub that feed the entire Philip Morris Plant. Work also included demolition of the adjacent Boiler House. Fugitive dust control means and methods were utilized so not to disturb ongoing operations to adjacent factory and employee parking. Site was graded and landscaped for future parking.