Procter and Gamble Ivorydale Tower Dismantlement
Location: St. Bernard, OH
Scope of Work:
Selective Demolition, Dismantlement
Project Detail:
This project consisted of selective dismantlement and removal of a former production tower, integral stairway and associated production equipment from the interior of the adjacent building. The production tower and stairs were carefully rigged, torch cut and lowered to the ground in pre-determined sections as to not interrupt live utilities and plant process pipes located directly adjacent to and below the demolition work area. Following removal of the tower and stairs, associated production equipment including a steel mezzanine were removed from the interior of the adjacent building.