Fortune 500 Locomotive Factory Selective Demolition
Location: Erie, PA
Scope of Work:
Selective Demolition, Dismantlement
Project Detail:
This selective demolition project included removal of (2) roof-top electrostatic precipitators, a concrete coal storage silo, multi story coal crusher/transfer buildings and associated overhead coal conveyors at Locomotive Assembly Plant. The precipitators and coal conveyors were systematically and sequentially rigged, torch-cut and lowered via a “piece by piece” dismantlement approach as to not impact directly adjacent manufacturing activities. Work was expedited within a tight, six (6) week time frame per owner’s request.